Electrical Tip: Overview of the Interconnection Rule


The interconnection rule, as noted in NEC 705.11, can be used in place of the 120% rule. If you use the interconnection rule, be sure to verify the following aspects:


1. The tap wires: check that there is enough space for the system to be successfully connected and there is a fusible disconnect (see below).


2. Line side tap rule:

  • The minimum wire size for a line side tap connection is 6AWG. However, If the fuses are 80A, Tap Wire Gauges should be 4 AWG. For the 200A Fuses, You need 4/0 AWG-rated Tap wires (See CTS June). 



3. Load side tap rule:

  • Consider the same limitations as a line side tap. The main difference is that with a load side tap, the connection occurs after the main breaker.


For questions regarding our electrical services, please email support@creng.solar.


 

Structural Tip: Tips for Salesforce Communication


Our Customer Success Team gathered a list of actions that can speed up response times on your Salesforce queries. To get the fastest solutions, try the following:


1. If the project is a restamp, remember to select "Restamp Required."


2. When your project is put on hold, you can reach out to our Customer Success (CS) Team via:

  • Email: support@creng.solar

  • Phone: (951) 203-5933

  • Slack: if you do not have a private slack channel yet, reach out via email or phone and we will be happy to set one up for you.


3. If the project is on hold and a comment was left, select "Continue Project" once the comment is addressed and you are ready for us to resume the project.


 

What would you like to see in next month's newsletter? Let us know.